C-130J Reborn After Five Years of Recovery from Hard Landing

Featured Image

The C-130J Super Hercules Makes a Remarkable Comeback

A hard landing at Ramstein Air Base in 2020 caused significant damage to a C-130J Super Hercules, leading to the first-ever field replacement of its wings. After being grounded for five years, the aircraft made a triumphant return to flight on July 26, 2025, marking a major milestone in military aviation.

The C-130J, assigned to the 37th Airlift Squadron (37th AS) under the 86th Airlift Wing (86th AW), was damaged during a hard landing on April 23, 2020. The incident resulted in extensive structural damage, including to the wings, engines, and landing gear. This necessitated a complex repair process that involved not only replacing the wings but also transporting them from the United States to Germany.

The 86th Airlift Wing's press release highlighted that the project required the production of specialized transport containers to move the new wings to Ramstein. This effort marked the first time a C-130J variant underwent such a wing replacement in the field, showcasing the adaptability and resourcefulness of the U.S. Air Force.

After spending over 30 days at Ramstein, the 402nd Expeditionary Maintenance Squadron (402nd EMS) and the 86th Maintenance Group (86th MG) completed the critical repairs. The aircraft, with the tail number 11-5376, was then returned to Robins Air Force Base, Georgia, where it underwent final checks before resuming operations.

The cause of the hard landing was attributed to pilot error, as determined by an Aircraft Accident Investigation Board (AAIB). The Mishap Pilot reduced engine power too early during the landing phase, which led to an excessive sink rate and a high g-load. This deviation from standard procedures resulted in significant damage to the aircraft.

Despite the severity of the damage, the decision was made to repair the aircraft rather than decommission it. Col. Lucas Buckley, commander of the 86th Maintenance Group, emphasized that this approach was more cost-effective and beneficial for the Air Force. The project involved collaboration between engineers, planners, and technicians across multiple units.

The next four years were dedicated to constructing new wings and developing transport containers for their movement. Once the parts arrived at Ramstein, the maintenance teams worked tirelessly to restore the aircraft to operational status. The effort culminated in a successful test flight on July 15, 2025, followed by the aircraft's return to the United States on July 28, 2025.

The U.S. Air Force operates approximately 300 C-130 H and J variants, serving as a vital component of its tactical airlift capability. Over 560 C-130J airframes are in use globally, accumulating more than 3 million flight hours. In June 2025, Lockheed Martin announced an extension of the C-130J’s wing life to 122,500 Equivalent Flight Hours, thanks to a multi-year durability test program.

The AAIB report detailed the specific actions that led to the hard landing, emphasizing the importance of adhering to established procedures. Both pilots failed to recognize and correct the excessive sink rate, contributing to the aircraft exceeding its limits. The damage was estimated at $20.9 million, underscoring the high stakes involved in such incidents.

The successful restoration of the C-130J is a testament to the dedication and expertise of the maintenance teams involved. Senior Master Sgt. Justin Jordan, quality assurance superintendent of the 86th MXG, described the moment the aircraft took off as "like watching a dream take flight." For the team, the aircraft represented more than just a machine—it symbolized resilience, history, and the spirit of aviation.

This remarkable achievement highlights the U.S. Air Force's commitment to maintaining operational excellence and its ability to overcome challenges through teamwork and innovation. The return of the C-130J after five years of repairs is a powerful reminder of the enduring strength and adaptability of military aviation.